Construction Projects


Projects Currently Under Construction.

H1635 QUARTERLINE RD., APPLE AVE.TO MCARTHUR RD.
Description: Mill and Resurface
Status: Currently Under Construction
Start Date: 7/7/2008
Projected Completion Date: 8/31/2008
Lane Closures: Street open to local traffic only.
Contractor(s) Performing Work Woodland Paving, Div. Comstock Park, MI 49321 (616) 785-6300

H-1630 CLAY AVE., THIRD ST. TO TERRACE ST.
Description: White topping and water main services work
Status: Currently Under Construction
Start Date: 8/1/2008
Projected Completion Date: 11/15/2008
Lane Closures: All lanes will be closed no traffic allowed.
Contractor(s) Performing Work: Kamminga & Roodvoets 3435 Broadmoor Ave. SE Grand Rapids, MI 49512
Emergency Contact #(616) 937-6302

H1577 Beidler St., Laketon Ave. to Southern Ave.
Description: Reconstruction – project will be completed in the spring of 2009
Status: Currently Under Construction
Start Date: 9/1/2008
Projected Completion Date: 11/30/2008
Lane Closures: Seek Alternate Route
Contractor(s) Performing Work: Jackson-Merkey Contractors, Inc. 555 E. Western Ave. Muskegon, MI 49441

Projects Proposed To Go Under Construction.

B-233 MUSKETAWA SHORELINE TRAIL CONNECTOR CORRIDOR
Description Construction of the Musketawa shoreline trail connector non-motorized bike path from Creston st., easterly to the US31 overpass, southerly across Laketon ave. just east of the expressway, then southerly to Keating ave. along the west side of Industrial blvd
Status: Not Yet Under Construction
Start Date: 4/6/2009
Projected Completion Date: 4/30/2009
Lane Closures: N/A
Contractor(s) Performing Work: Thompson Brothers, Inc. 388 W. McMillan RD. Muskegon, MI 49445